Project Update 06/30/2016

WORK COMPLETED LAST WEEK: The performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: 1. Excavation, loading, and haul-off of excavated spoils required for Storm Trap stormwater retention facility installations. 2. Receipt and stockpile of granular materials for stormwater retention facility subgrade preparation and backfill.… Continue reading

More

Project Update 6/24/2016

WORK COMPLETED LAST WEEK: The performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: 1. Excavation, loading, and haul-off of excavated spoils required for Storm Trap stormwater retention facility installations. 2. Receipt and stockpile of granular materials for stormwater retention facility subgrade preparation and backfill.… Continue reading

More

Project Update 06/17/2016

WORK COMPLETED LAST WEEK: The performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: Excavation, loading, and haul-off of excavated spoils required for Storm Trap stormwater retention facility installations. Receipt and stockpile of granular materials for stormwater retention facility subgrade preparation and backfill. Preparation of… Continue reading

More

Project Update 6/9/2016

WORK COMPLETED LAST WEEK: The performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: Excavation, loading, and haul-off of excavated spoils required for Storm Trap stormwater retention facility installations. Receipt and stockpile of granular materials for stormwater retention facility subgrade preparation and backfill. Preparation of… Continue reading

More

Project Update 6/3/2016

WORK COMPLETED LAST WEEK: ┬áThe performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: Excavation, loading, and haul-off of excavated spoils required for Storm Trap stormwater retention facility installations. Receipt and stockpile of granular materials for stormwater retention facility subgrade preparation and backfill. Preparation of… Continue reading

More

Project Update 05/26/2016

WORK COMPLETED LAST WEEK: The performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: Excavation, loading, and haul-off of excavated spoils required for Storm Trap stormwater retention facility installations. Receipt and stockpile of granular materials for stormwater retention facility subgrade preparation and backfill. Preparation of… Continue reading

More

Project Update 05/20/2016

WORK COMPLETED LAST WEEK: The performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: 1. Excavation, loading, and haul-off of excavated spoils required for Storm Trap stormwater retention facility installations. 2. Receipt and stockpile of granular materials for stormwater retention facility subgrade preparation and backfill.… Continue reading

More

Project Update 05/12/2016

WORK COMPLETED LAST WEEK: The performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: 1. Stripping and stockpiling of topsoil, as required, to allow excavation for Storm Trap installations. 2. Excavation, loading, and haul-off of excavated spoils required for Storm Trap stormwater retention facility installations.… Continue reading

More

Project Update 05/06/2016

WORK COMPLETED LAST WEEK: The performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: 1. Stripping and stockpiling of topsoil, as required, to allow excavation for Storm Trap installations. 2. Excavation, loading, and haul-off of excavated spoils required for Storm Trap stormwater retention facility installations.… Continue reading

More

Project Update 4/29/2016

WORK COMPLETED LAST WEEK: The performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: 1. Stripping and stockpiling of topsoil, as required, to allow excavation for Storm Trap installations. 2. Excavation, loading, and haul-off of excavated spoils required for Storm Trap stormwater retention facility installations.… Continue reading

More