Project Update 9/1/2016

WORK COMPLETED LAST WEEK: Continued installation of the new three-inch force main from new stub previously installed into Wescott Part from the new Storm Manhole No. 5 located in Farnsworth Lane immediately west of Western Avenue, toward the Rain Harvesting System Wet Well. Completed installation of precast backstop post foundations atop the Storm Trap Stormwater… Continue reading

More

Project Update 8/26/2016

WORK COMPLETED LAST WEEK: The performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: Completed installation of all new catch basins, precast lids, and adjustment of frames in preparation of final grading and final restoration of the roadways. Completed dewatering activities required for the installation… Continue reading

More

Wescott Park Elementary School Parents Road Closure Info

Due to construction on Farnsworth Avenue as part of the Wescott Park Stormwater Management Project, we ask that parents and students utilize alternative routes.  Please CLICK HERE to see a map detailing the road closures currently in place. For current information on the status of this project please continue to visit this website which is… Continue reading

More

Project Update 8/18/2016

WORK COMPLETED LAST WEEK: The performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: Completed installation of all new 42” storm piping. Installed the last Stormwater Structure, located in the intersection of Farnsworth Lane and Ellendale Drive. Poured miscellaneous concrete fillets in the last Stormwater… Continue reading

More

Project Update – 8/12/2016

WORK COMPLETED LAST WEEK: The performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: Continued installation of the new 42” storm piping between Sunnyside Circle and Ellendale Drive. Replaced existing Catch Basins in Sunnyside Circle south of Farnsworth Lane. Installed Catch Basins and associated 18”… Continue reading

More

Project Update – 8/4/2016

WORK COMPLETED LAST WEEK: The performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: Continued placement of stripped topsoil across the top of the clay backfill over the top of the Storm Trap stormwater retention facility. Set a portion of the precast concrete backstop post… Continue reading

More

Project Update 7/29/2016

WORK COMPLETED LAST WEEK: The performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: Installed the last remaining precast concrete panel of the 1,722 pieces required to complete the Storm Trap concrete stormwater storage facility. Completed placement of clay backfill over the top of the… Continue reading

More

Project Update 7/22/2016

WORK COMPLETED LAST WEEK: The performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: Received delivery of the last remaining precast concrete panel required to close the Storm Trap stormwater storage facility. Installed the last remaining precast concrete panel of the 1,722 pieces required to… Continue reading

More

Project Update 7/14/2016

WORK COMPLETED LAST WEEK: The performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: 1. Completed receipt and stockpiling of granular materials for the backfill of the last portion of the stormwater retention facility. 2. Received deliveries of the last remaining precast Storm Trap concrete… Continue reading

More

Project Update 7/08/2016

WORK COMPLETED LAST WEEK: The performance of the following activities is a continuance of activities from the week(s) prior, unless specifically noted as completed: Completed the last of the excavation, loading, and haul-off of excavated spoils required for Storm Trap stormwater retention facility installation. Received and stockpiled granular materials for the last portion of the… Continue reading

More