Project Update 11/11/2016

WORK COMPLETED LAST WEEK: 1. Completed placement of sod in the outfield of the ball fields in Wescott Park. 2. Continued watering of new sod placed in the outfield in Wescott Park. 3. Completed installation and started up the Irrigation System for Wescott Park. 4. Completed installation and started up the Rainwater Harvesting System in… Continue reading

More

Project Update 11/03/2016

WORK COMPLETED LAST WEEK: 1. Completed watering of new sod placed in parkways disturbed by construction. 2. Continued placement of sod in Wescott Park in new outfield. 3. Continued watering of new sod placed in Wescott Park in new outfield, along the west asphalt path, and off the northwest corner of Wescott Park. 4. Continued… Continue reading

More

Project Update 10/26/2016

WORK COMPLETED LAST WEEK: 1. Continued watering of new sod placed in parkways disturbed by construction. 2. Began placement of sod in the outfield of the ball fields in Wescott Park. 3. Began watering of new sod placed in the outfield in Wescott Park. 4. Planted remaining trees in Wescott Park. 5. Continued final terminations,… Continue reading

More

Project Update 10/20/2016

WORK COMPLETED LAST WEEK: 1. Continued watering of new sod placed in parkways disturbed by construction. 2. Removed perimeter temporary chain-link fencing from Wescott Park prior to placement of new sod within the Park. 3. Completed placement, grading, and compaction of baseball infield granular. 4. Completed final grading within Wescott Park in preparation for new… Continue reading

More

Project Update 10/13/2016

WORK COMPLETED LAST WEEK: Continued placement, grading, and compaction of baseball infield granular. Continued final grading of topsoil within Wescott Park in preparation for new sod. Completed fine grading and placement of sod in parkway areas between new curbs and sidewalks along the south side of Farnsworth Lane and associated side streets affected by construction.… Continue reading

More

Project Update 10/6/2016

WORK COMPLETED LAST WEEK: Began and completed videotaping of storm sewers for record purposes required by the Contract. Cleaned new roadway surfaces of dirt and debris due to construction activities. Cleaned catch basins, located in the limits of construction, of debris and removed inlet protection filters to put new storm sewer system into final service.… Continue reading

More

Project Update 9/30/2016

WORK COMPLETED LAST WEEK: Completed installation of underground site electrical conduits and associated appurtenances between the wet well and control pad locations for the Rainwater Harvesting System. Completed installation of underground site mechanical piping and associated appurtenances between the wet well and control pad locations for the Rainwater Harvesting System. Prepared subgrade for miscellaneous concrete… Continue reading

More

Project Update 9/23/2016

WORK COMPLETED LAST WEEK: Completed installation of the new three-inch force main in Wescott Park up to the Rainwater Harvesting System. Completed installation of underground piping associated with domestic water services to the drinking fountain and Rainwater Harvesting System. Prepared subgrade for miscellaneous concrete pads for the Rainwater Harvesting System and associated control and valve… Continue reading

More

Project Update 9/16/2016

WORK COMPLETED LAST WEEK: Continued installation of the new three-inch force main in Wescott Park toward the Rainwater Harvesting System. Began installation of underground piping associated with domestic water services to the drinking fountain and Rainwater Harvesting System. Began preparation of subgrade for miscellaneous concrete pads for the Rainwater Harvesting System and associated control and… Continue reading

More

Project Update 9/9/2016

WORK COMPLETED LAST WEEK: 1. Continued installation of the new three-inch force main to serve the new Rain Harvesting System Wet Well. 2. Received delivery of Rainwater Harvesting System enclosure with controls, pumps, and appurtenances. 3. Continued the import, pulverizing, placement, and rough grading of stockpiled topsoil atop the Storm Trap Stormwater Storage Facility. 4.… Continue reading

More