Project Update 11/11/2016

WORK COMPLETED LAST WEEK: 1. Completed placement of sod in the outfield of the ball fields in Wescott Park. 2. Continued watering of new sod placed in the outfield in Wescott Park. 3. Completed installation and started up the Irrigation System for Wescott Park. 4. Completed installation and started up the Rainwater Harvesting System in… Continue reading

More

Project Update 11/03/2016

WORK COMPLETED LAST WEEK: 1. Completed watering of new sod placed in parkways disturbed by construction. 2. Continued placement of sod in Wescott Park in new outfield. 3. Continued watering of new sod placed in Wescott Park in new outfield, along the west asphalt path, and off the northwest corner of Wescott Park. 4. Continued… Continue reading

More

Project Update 10/26/2016

WORK COMPLETED LAST WEEK: 1. Continued watering of new sod placed in parkways disturbed by construction. 2. Began placement of sod in the outfield of the ball fields in Wescott Park. 3. Began watering of new sod placed in the outfield in Wescott Park. 4. Planted remaining trees in Wescott Park. 5. Continued final terminations,… Continue reading

More

Project Update 10/20/2016

WORK COMPLETED LAST WEEK: 1. Continued watering of new sod placed in parkways disturbed by construction. 2. Removed perimeter temporary chain-link fencing from Wescott Park prior to placement of new sod within the Park. 3. Completed placement, grading, and compaction of baseball infield granular. 4. Completed final grading within Wescott Park in preparation for new… Continue reading

More

Project Update 10/13/2016

WORK COMPLETED LAST WEEK: Continued placement, grading, and compaction of baseball infield granular. Continued final grading of topsoil within Wescott Park in preparation for new sod. Completed fine grading and placement of sod in parkway areas between new curbs and sidewalks along the south side of Farnsworth Lane and associated side streets affected by construction.… Continue reading