Project Update 10/6/2016

WORK COMPLETED LAST WEEK: Began and completed videotaping of storm sewers for record purposes required by the Contract. Cleaned new roadway surfaces of dirt and debris due to construction activities. Cleaned catch basins, located in the limits of construction, of debris and removed inlet protection filters to put new storm sewer system into final service.… Continue reading

More

Project Update 9/30/2016

WORK COMPLETED LAST WEEK: Completed installation of underground site electrical conduits and associated appurtenances between the wet well and control pad locations for the Rainwater Harvesting System. Completed installation of underground site mechanical piping and associated appurtenances between the wet well and control pad locations for the Rainwater Harvesting System. Prepared subgrade for miscellaneous concrete… Continue reading

More

Project Update 9/23/2016

WORK COMPLETED LAST WEEK: Completed installation of the new three-inch force main in Wescott Park up to the Rainwater Harvesting System. Completed installation of underground piping associated with domestic water services to the drinking fountain and Rainwater Harvesting System. Prepared subgrade for miscellaneous concrete pads for the Rainwater Harvesting System and associated control and valve… Continue reading

More

Project Update 9/16/2016

WORK COMPLETED LAST WEEK: Continued installation of the new three-inch force main in Wescott Park toward the Rainwater Harvesting System. Began installation of underground piping associated with domestic water services to the drinking fountain and Rainwater Harvesting System. Began preparation of subgrade for miscellaneous concrete pads for the Rainwater Harvesting System and associated control and… Continue reading

More

Project Update 9/9/2016

WORK COMPLETED LAST WEEK: 1. Continued installation of the new three-inch force main to serve the new Rain Harvesting System Wet Well. 2. Received delivery of Rainwater Harvesting System enclosure with controls, pumps, and appurtenances. 3. Continued the import, pulverizing, placement, and rough grading of stockpiled topsoil atop the Storm Trap Stormwater Storage Facility. 4.… Continue reading